| Golden Hills Wind Project |
|
|
 |
|
|
Facility: A wind energy facility with a peak generating capacity of up to 400 megawatts.
Location: Sherman County
Status:
The Council has approved a site certificate. The facility is not yet under construction. The applicant has submitted a request to amend the site certificate to extend deadlines to begin and complete construction by two years.
Certificate Holder:
BP Alternative Energy of North America, Inc.
Website: www.goldenhillswind.com
Contact:
Matt Duffy
BP Wind Energy North America, Inc.
700 Louisiana St, 33rd Floor
Houston, TX 77002
(713) 354-6716
Department of Energy Staff: Chris Green
Original site certificate signed: June 18, 2009
History:
- April 11, 2007: Applicant submitted a Notice of Intent.
- July 6, 2007: Department of Energy issued a Project Order.
- August 10, 2007: Applicant submitted a preliminary application.
- August 4, 2008: Date of Filing (application complete).
- October 6, 2008: Department of Energy issued a draft proposed order
- May 15, 2009: Council approved a site certificate.
- June 18, 2009: Effective date of the site certificate.
- December 15, 2011: Request for Amendment #1 received
Documents:
|
|
|
|