BETC - Renewable Energy Projects
Introduction
Tier One - projected facility costs < $500,000
Tier Two - projected facility costs >/= $500,000 but < $6,000,000
Tier Three - projected facility costs >/= $6,000,000
Introduction

 
Red Envelope Sign up to receive BETC email updates.
 
By subscribing, you will be automatically notified of any changes in the information on this page.
 
 
 
Oregon Laws, 2010, Chapter 76, Section 2 limits the amount of potential tax credits for facilities (projects) using or producing renewable energy resources or listed as renewable energy resources under ORS 469.185 to $300 million for the biennium ending June 30, 2011. To meet these limits, ORS 469.195(2) established a tiered priority system and the criteria that the Oregon Department of Energy (Department) Director may consider in deciding whether to grant a Business Energy Tax Credit (BETC) for these facilities. The statute requires the Director to subject facilities with higher projected costs to closer scrutiny and compare facilities of similar costs against each other.
 
ELIGIBILITY
 
To be eligible to apply an applicant must meet the following requirements:
  • Be a trade, business or rental property owner with a business site in Oregon or be an Oregon non-profit organization, tribe, or public entity that partners with an Oregon business or resident;
  • Own or be the contract buyer of the facility; and
  • Use the equipment or lease it to another person or business in Oregon; and

  • Not have started physical construction; and

  • Must complete the facility and receive final certification before by July 1, 2012.
 
PROCESS
 
Applications will be processed differently depending on the projected facility costs. Click on the following links to be directed to the appropriate tier for your facility (project) based on your projected facility costs:
 

Tier One - projected facility costs < $500,000
 
PROCESS
 
To apply for a tier one Business Energy Tax Credit complete the Tier One General Application and the appropriate appendix for your facility. Submit your completed application and review charge to the Oregon Department of Energy at:
Oregon Department of Energy
Attn: BETC Renewable – Tier One
625 Marion St. NE
Salem, OR 97301
Your application will be reviewed and processed on an ongoing basis subject to the tax credit limitations published by the Department. Applications will be processed in the order they are received and may be rejected once all available tax credits have been issued for this tier. If your application is rejected on the basis that there are no more tax credits available, you may be issued a refund.
 
FORMS
 

  • Tier One General Application Instructions
 PDF 
 
  • Tier One General Application
 PDF  Word 
  • Appendix No. 1 – Biomass, Wind, Hydro & Geothermal
 PDF 
 Word 
  • Appendix No. 2 – Biomass Infrastructure 
 PDF 
 Word 
  • Appendix No. 3 – Photovoltaic
 PDF 
 Word 
          » PV Maximum Eligible Cost Calculator
 
   Excel 
 
  • Appendix No. 4 – Solar Thermal
 PDF 
 Word 
         
          » ST Maximum Eligible Cost Calculator
   
 Excel 
 

Tier Two - projected facility costs >/= $500,000 but < $6,000,000
 

Information about the review process for Tier Two applications received in June 2010 can be found on the Tier Two June-August 2010 webpage. 
 
The next round of Tier Two applications will be accepted in October 2010. Please check this website mid-September 2010 for the October 2010 Tier Two Opportunity Announcement and application forms. Please sign up for BETC e-mail updates at the top of this webpage to receive information.
 
PROCESS
 
All Tier Two facilities will be required to submit their application through a competitive application process. When available, please review the Tier Two BETC Opportunity Announcement for all the requirements to submit a Tier Two application. These requirements are in addition to the requirements in statute and rule. 
 
TENATIVE SCHEDULE (subject to change)

 October–December 2010 Funding Period
 Due Date (subject to change)
 Date of Issuance 
 Mid Sept, 2010
 Date Applications Accepted 
 October 1, 2010
 Written Questions Due
 October 13, 2010 by 5PM PST
 Questions & Answers Posted
 October 20, 2010
 Applications Due 
 October 29, 2010 by 5PM PST
 Technical Review & Scoring
 November & December 2010
 BETC Preliminary Certificate Notification
 Late December 2010

 
FORMS
 
In mid-September 2010, the Tier Two Opportunity Announcement and application forms for the October-December 2010 funding period will be available. Please sign up for BETC e-mail updates to be notified.

QUESTIONS & ANSWERS
 
Questions, including requests for explanations of the meaning or interpretation of provisions of the opportunity announcement and application forms, must be submitted via e-mail, arrive by the date and time specified in the schedule above, and be addressed to the attention of only the SPC (betcoa@odoe.state.or.us). To help ensure questions are answered and responses are posted appropriately, please identify Tier Two in your subject line.
 
Answers to questions submitted will be posted every few days up to the final due date.
  
October 2010 Posted Questions & Answers (updated August 5, 2010)
 
Archived Questions and Answers from Prior Funding Periods
June 2010 Posted Questions & Answers (updated June 17th, 2010)
 
 

Tier Three - projected facility costs >/= $6,000,000

 
Tier Three applications received in June & July 2010 are currently being reviewed, information about the review process can be found on the Tier Three June-November 2010 webpage. 
 
Please sign up for BETC e-mail updates at the top of this webpage to receive updates about the next Tier Three funding period.
 
PROCESS
 
All tier three facilities will be required to submit their application through a competitive application process. When available, please review the BETC Opportunity Announcement - Tier Three for all the requirements to submit a tier three application. These requirements are in addition to the requirements in statute and rule. When announced, this webpage will contain the schedule and forms to apply under a tier three funding period.
    
QUESTIONS & ANSWERS
 
Questions, including requests for explanations of the meaning or interpretation of provisions of the opportunity announcement, must be submitted via e-mail, arrive by the date and time specified in the schedule above, and be addressed to the attention of only the SPC (betcoa@odoe.state.or.us). To help ensure questions are answered and responses are posted appropriately, please identify Tier Three in your subject line.
 
Answers to questions submitted will be posted every few days up to the final due date 
 
Archived Questions and Answers from Prior Funding Periods
June 2010 Posted Questions & Answers (updated June 17th, 2010)
 
 

 